CASE STUDY 3: Hewitt Associates, Moor, London 2005


Location Moor, London
Duration 20 Weeks
Client Going Live Ltd, Sleaford, Lincolnshire
Scope of Works Installation of:

3500 Category 6 Network Cables
Fiber Optic Backbone Cabling
Voice Backbone Cabling
Server Cabinets & Accessories
Cat 6 Testing & Certification to ISO/1EE Class E Link Test
Fiber Optic Testing & Certification to 1000BASE-SX (Gigabit Ethernet)
25-Year 3M Volition Warranty.
Project Focus
Hewitt Associates are the world's largest provider of multi-service HR business process outsourcing (BPO), and the only firm fully integrating HR outsourcing and consulting having approximately 23,000 employees in 30 countries.

The organisation had decided to re-locate from there existing London offices to a newly constructed offices in More, London. Overbury Construction were chosen to carry out the fit out of 4 floors which included the construction of open office area’s, receptions, meeting rooms and media rooms.

Netlink Cabling & Security Solutions was chosen by Going Live Ltd to provide a team of engineers to install and supervise the contract on there behalf, the work also included the supervision of other contractors also working on the project.
Category 6 cabling
The network cabling infrastructure included the installation of over 3,500 Krone TrueNet Category 6 UTP network cables to provide the client with network, telephone & video connectivity.

The cabling work involved installing a new Cat 6 structured cabling system as part of the new fit out which included installing cabling within new offices, reception areas, video conferencing rooms and open plan work areas.
Four new communication rooms were built to distribute the cabling over four floors each communication room had approx 1000 Cat 6 network points, 320 voice links, 25 ISDN links & 24 Core fibre links.

The new Cat 6 cabling was terminated onto Krone TrueNet 24-way patch panels within new 42U APF computer frames, and both single and dual faceplates at the user outlet contained within floor boxes. Krone TrueNet RJ-K CL UTP Jacks were used to connect the cabling which offer superior performance.

Following the installation and termination of the Category 6 cabling, testing was successfully carried out prior to the handover to the client using a Fluke level 111 Category 6 network cabling tester, providing evidence that every cable installed meets the requirements of TIA/EIA-568-B.2-1 test standards.

A full and comprehensive set of test results, including drawings showing outlet locations and cable routes were submitted to both the client and ADC Krone to verify there strict installation and test standards have been met.


Fibre optic backbone cabling
Each communication room located on all floors was connected to the main communication room using multimode fibre optic cabling. Interlinks were also installed between each of the communication room to add resilience to the network.

The client also required singlemode fibre optic cabling installing between each communication room to transmit high quality video, used for video conference calls around the world.

SC type factory polished fibre connectors were used and spliced onto the fibre optic cabling using a core alignment fusion splicer to terminate the cabling ensuring the lowest possible losses.

Testing & Certification of the fibre optic cabling was carried out using a Fluke certification tester & OTDR.
Voice backbone cabling
The new Avaya PABX Telephone switch was installed within the basement communication room and required a new wall mounted distribution frame to terminate the exchange lines and also distribution cabling around the site.

320 pair voice backbone cabling links were installed to each communication room and terminated within the APF communication frames on all four floors along with additional 50 pair voice links terminated for use as dedicated ISDN lines.

Voice backbone Interlinks were also installed between each of the communication room to add resilience to the network.

The voice cabling was terminated onto Krone TrueNet 50 port voice patch panels which housed within the each of the APF communication frames in all four communication rooms, allowing telephone connections to be simply patched between the voices & structured cabling patch panels using standard RJ45 patch cords.



  Category 5e/6 Cabling - Single and Multimode Fiber Optic Cabling - Voice Cabling - Fiber and Copper Testing - Cabling Surveys - CCTV - 25 Year Warranties